Griffith Woods Transmission Line Pole Replacement

Project Update:
February 16, 2010
Construction is complete on the Griffith Woods Transmission Line Pole Replacement project. AltaLink is now working with The City of Calgary to reclaim the right-of-way (construction area) in the park. The reclamation work will take place throughout the spring and summer of 2010 with some followup activities in 2011.

About the project:
AltaLink is currently replacing a portion of two transmission power lines that run through Griffith Woods Park. The current double pole, single circuit 138 kV transmission lines, named 3L and 150L, will be replaced with double circuit structures.

History of the project:
A Facilities Application was submitted to the Alberta Utilities Commission (AUC) on December 22, 2008 and in June of 2009 the AUC held a public hearing to listen to stakeholder concerns regarding AltaLink's application. On August 18, 2009 the AUC approved the preferred option to replace the structures on a portion of two parallel power lines, changing them from single circuit to double circuit structures.

Why does this work need to occur?
The Griffith Woods Transmission Line Pole Replacement project will address the reliability and safety concerns with the current lines and reduce the foot print of the line within the existing right-of-way in Griffith Woods Park. The narrower footprint of the transmission line reduces the number of danger trees that could contact the lines and would therefore need to be trimmed or removed.

Project timeline
November 2009 - Surveying work
November/December 2009 -  Brushing (vegetation management) to create safe work spaces in preparation of construction
January 2010 -  Start of construction
March 2010 - Construction completion, right-of-way reclamation with The City of Calgary Parks

Pathway Closures
During construction, access to the park or pathways may be restricted to ensure the safety of all park users. Pathway closures will be clearly marked with signs and security personnel will be present to monitor the site.

Our commitment to the community and the environment
We are committed to working with the Discovery Ridge community and all interested stakeholders to ensure that the project is completed successfully with minor impact to residents and park users. We will respect the park while construction occurs and will ensure that immediately following project completion the construction area is restored as directed by The City of Calgary Parks.

Additional information
For further information about the history of the project and the consultation efforts to date, please review the section below ‘Related attachments'.

Contact information
If you have any questions regarding this project please feel free to contact us at 1-877-267-1453 or siting.consultation@altalink.ca.

Related Attachments

Letter delivered to residents in the communities of Discovery Ridge, Signal Hill and Springbank Hill in July 2010. The letter addresses AltaLink's plan to make an application to Alberta Infrastructure for consent to move approximately 3.5 km of an existing double-circuit, 138 kV transmission line, called 3L/150L, out of Griffith Woods Park and into the Transportation/Utility Corridor at the west end of Glenmore Trail.

Questionnaire delivered to residents in the communities of Discovery Ridge, Signal Hill and Springbank Hill in July 2010. The questionnaire seeks feedback from residents on their preferred location of the AltaLink transmission line, called 3L/150L, that currently runs through Griffith Woods Park.

October2009Letter.pdf  ( 957.8 KB )

Letter delivered to residents in Discovery Ridge in October 2009.

Letter delivered to landowners in Discovery Ridge in October 2009.

March2009Letter.pdf  ( 69.7 KB )

Letter delivered to residents in Discovery Ridge in March 2009.

openhousepanels08.pdf  ( 4.4 MB )

AltaLink held an open house and Q&A session for the residents of Discovery Ridge on Wednesday, September 17, 2008. This booklet is a smaller version of the panels at the open house and was given to those in attendance.

Letter sent to all residents in Discovery Ridge in August 2008.

GriffithWoodsMap.pdf  ( 1.1 MB )

Map of the transmission line in Griffith Woods Park - new as of August 2008.

Comparison of options.pdf  ( 83.7 KB )

Table that compares the options AltaLink has considered for the transmission line maintenance.

Brochure that was sent to all Discovery Ridge residents in February 2008.

GriffithWoodsLetter.pdf  ( 69.5 KB )

Letter that was sent along with the brochure in February 2008.

AltaLink hosted an open house for residents of Discovery Ridge on Monday, December 3. Open this document to view the information that was given to all attendees.

Griffith Woods Map.pdf  ( 108.5 KB )

Map of the Griffith Woods Park with AltaLink's current and proposed transmission lines.

CommunityBoardNotice.pdf  ( 20.9 KB )

This notice of the open house was placed around the Discovery Ridge Community.

This letter was sent to all Discovery Ridge residents to invite them to the open house.

LetterGriffithWoods.pdf  ( 546.8 KB )

Letter that was sent to all Discovery Ridge landowners in August 2007.

Original brochure that was delivered to adjacent homeowners in June 2007.