Grid Connections

How to connect

We are pleased to provide assistance to customers wishing to connect to the portion of Alberta’s transmission system that is owned and operated by AltaLink. 

In order to connect to Alberta’s grid, you will need to follow the Alberta Electric System Operator’s (AESO) Connection Process. The process identifies the steps required for all industry partners involved in a new connection to the grid, including the customer, the AESO, the Alberta Utilities Commission (AUC) and AltaLink.

roles of each industry partner 

Customer

  • Manages project progress through the process
  • Applies for access to the transmission system
  • Authorizes the project
  • Completes connection studies and Connection Proposal in conjunction with the TFO or an independent consultant
  • Funds the project

Alberta Electric System Operator (AESO)

  • Endorses and files the need for transmission facilities
  • Leads the connection process to ensure that all customers are provided with open and fair access to the transmission system
  • Informs landowners and stakeholders of the need for transmission facilities
  • Administers access to the transmission system
  • Manages the Connection Queue
  • Provides governance through rules, regulations, policies, standards and guidelines

Alberta Utilities Commission (AUC)

  • Manages the public interest
  • Approves Need and Facilities Applications
  • Provides governance through legislation and regulations

AltaLink

  • Owns and operates the transmission facilities
  • Consults landowners and stakeholders on the new transmission facilities
  • Builds new transmission facilities
  • Manages connection projects, including project management and financial requirements (all necessary contracts/agreements)
  • Completes connection studies and Connection Proposal (on behalf of the Customer, if requested)