• Central Alberta Transmission Projects

Red Deer Area Transmission Development

Project overview

Red Deer and the surrounding areas have grown significantly in recent years and the demand for electricity has increased. Transmission system reinforcements are required to make sure homes, farms and businesses continue to have a reliable supply of electricity for years to come.

Stage 1 of the development was completed in late 2013. On July 29, 2014, AltaLink received approval from the Alberta Utilities Commission (AUC) to construct componants that fall under stages 2 and 3 of the development.

Construction activities are currently underway in the Ponoka, Didsbury, Sylvan Lake and Red Deer areas. Construction in the Innisfail area is scheduled to begin in the summer or fall of 2015. Construction on all project components is expected to be complete by the summer or fall of 2016.

Click here for the typical stages of substation construction.
Click here for the typical stages of transmission line construction.

More information about each stage of the project, including newsletters and maps can be found below.

Project updates

Path and lane closures in the City of Red Deer May, 2015 

In early May we plan to begin removing the existing portion of the 80L transmission line in the Riverlands and West Park areas. This work will take place along the riverbank southwest of Taylor Drive to the area just north of Welton Crescent and along Walker Boulevard towards Highway 2. During construction there will be periodic pathway and lane closures in the Riverlands and West Park areas.

  • Walker Boulevard traffic will be reduced to one lane while work is taking place in the area. Parking along Walker Boulevard will not be allowed during this time.

Helicopter activity in the City of Red Deer March 21-23, 2015 (weather dependent)   AltaLink will be using a helicopter to install bird diverters on a section of transmission line over the Red Deer River. This section of transmission line is located directly west of the southbound 50 Avenue bridge.  

This work is part of AltaLink's Avian Protection Plan, a management system designed to reduce the impact our transmission facilities can have on birds. AltaLink was the first Canadian utility to develop such a plan.

Pathway closures in the City of Red Deer March 9-20, 2015 

  • pathway closures from Taylor Drive on the south side of the Red Deer River, west to the pathway entrance at Warwick Drive

Helicopter activity in the City of Red Deer week of February 16, 2015

Starting on Monday, February 16 AltaLink will be using a helicopter in the City of Red Deer between the areas of 82 Street and 67 Street (just north of Parsons Close). A specialized helicopter will be used to fly assembled transmission structures into place for the rebuild of the existing 80L transmission line. Helicopters can reduce the amount of time required to complete work in the area and minimize the amount of construction traffic and workspace area required along the right-of-way.  

The activity will take place during daylight hours. It is only expected to take a couple of days, depending on the weather conditions.

To ensure the safety of the public during helicopter activity, there will be periodic lane closures and traffic stoppages at the following locations:

  • 45 Avenue
  • 47 Avenue
  • Northland Drive
  • Parsons Close
  • 77 Street

Path and lane closures in the City of Red Deer February 9-15, 2015 

  • pathway closures on either side of Gaetz Avenue, crossing the river 
  • single lane closure on west bound Riverside Drive (in the area between the Lion's Campground and 46a Avenue
  • single land closure on 58 Street just west of Gaetz Avenue 

Implosive connectors in Red Deer County February 8-13, 2015 

Construction activities are underway on rebuilding the 648L and 637L transmission lines between Benalto and southwest Red Deer.  

If you live or work near the project, you may hear some loud explosive sounds over the next few weeks and months. During the wire stringing process we will be fusing portions of wire together using implosions. The implosions do not pose a safety risk to surrounding residences; however, they will emit a loud explosive sound. There should not be more than a few loud explosive sounds on days when this work is scheduled to occur. This work will be completed during day light hours only. Thank you for your patience.

Periodic lane and trail closures in the City of Red Deer 

Construction activities are underway in the City of Red Deer to rebuild the existing 80L transmission line between the areas of 82 Street and Taylor Drive. 

As a result of some of the construction activities, there will be periodic single lane closures, speed reductions and momentary traffic stoppages to ensure the safety of commuters along these areas:

  • North and south bound Riverside Drive
  • East bound 58 Street
  • North and south bound Gaetz Avenue crossing the Red Deer River
  • Either direction on 67 Street crossing Riverside Drive
  • 46 Avenue between Riverside Drive and 63 Street
  • The roundabout near 54 Avenue and 55 Street
  • Either direction on 77 Street
  • Parsons Close

There will also be trail closures required at times at these locations:

  • Trans Canada Trail Bridge (from the east side of the Red Deer River to the west side of the Red Deer River)
  • Pathways on the northwest side of the Red Deer River on either side of the Gaetz Avenue Bridge
  • Mountain bike paths crossing the right-of-way north and east of the Mountain Bike Park
  • South of 77 Street to Parsons Close

Activities between 67 Street and Taylor Drive are expected to be complete in mid February 2015. Activities between 67 Street and 82 Street are expected to be complete in Spring 2015. We apologize for the inconvenience.

Read AltaLink's letter to the editor of the Red Deer Advocate - printed on Friday, October 10, 2014

There has been some misinformation in the public recently about AltaLink's Red Deer Area Transmission Development. On October 7, 2014 AltaLink submitted a letter to the editor in order to clarify details about the project and AltaLink's processes, especially with respect to the portion of the project that goes through the Pines neighbourhood in the City of Red Deer.

New transmission line east of Lacombe (423L) 
As part of Stage 3 of the development, AltaLink is also proposing to build a new transmission line, called 423L, east of Lacombe. AltaLink included this component in the original application that was filed with the AUC but we are continuing to look at our options for the proposed new transmission line. As a result, the AUC has postponed its consideration of the 423L component. AltaLink is continuing to communicate with stakeholders near the proposed 423L transmission line as the project progresses and we submitted a revised application to the AUC for the 423L project on October 6, 2014.

Project details

The proposed Red Deer Area Transmission Development is divided into five stages.

  • Stage 1substation upgrades: upgrading six substations
  • Stage 2transmission line rebuilds: rebuilding nearly 75 kilometres of existing transmission lines in the Red Deer and Sylvan Lake areas
  • Stage 3new substations and transmission lines: building new substations near Ponoka, Innisfail and Didsbury and building approximately 50 kilometres of new transmission lines near the substations and east of Lacombe
  • Stage 4removing existing transmission lines: removing approximately 75 kilometres of transmission line from Wetaskiwin to Lacombe and approximately 25 kilometres of transmission line from Red Deer to Innisfail
  • Stage 5 - 166L transmission line rebuild: rebuilding approximately 15 kilometres of existing transmission line and upgrading an existing substation near Didsbury

Listen to our radio advertisements...

Newsletters and maps

February 2015

 January 2015

October 2014

August 2014

January 2014

July 2013

January 2013

November 2012

August 2012

November 2011

June/July 2011

December 2014

October 2014

August 2014

January 2014

August 2013

July 2013

May 2013

February 2013

June 2012

February 2012

January 2012

July 2011

   

In This Section
Projects
Rewarding Careers at AltaLink
Rewarding Careers at AltaLink
At AltaLink, we are doing everything in our power to attract the best and brightest.
Did You Know?
Workplace Safety at AltaLink
A reliable transmission system keeps costs low by connecting diverse sources of power generation to the grid.