• Central Alberta Transmission Projects

Red Deer Area Transmission Development

Project overview

Red Deer and the surrounding areas have grown significantly in recent years and the demand for electricity has increased. Transmission system reinforcements are required to make sure homes, farms and businesses continue to have a reliable supply of electricity for years to come.

Stage 1 of the development was completed in late 2013. On July 29, 2014, AltaLink received approval from the Alberta Utilities Commission (AUC) to construct componants that fall under stages 2 and 3 of the development.

Currently we are preparing for construction activities in the Ponoka, Didsbury, Sylvan Lake and Red Deer areas. Construction in the Innisfail area is scheduled to begin in the summer or fall of 2015. Construction on all project compnants is expected to be complete by the summer or fall of 2015.

Click here for the typical stages of substation construction.
Click here for the typical stages of transmission line construction.

More information about each stage of the project, including newsletters and maps can be found below.

Please note: As part of Stage 3 of the development, AltaLink is also proposing to build a new transmission line, called 423L, east of Lacombe. AltaLink included this component in the original application that was filed with the AUC but we are continuing to look at our options for the proposed new transmission line. As a result, the AUC has postponed its consideration of the 423L component. AltaLink will continue to communicate with stakeholders near the proposed 423L transmission line as the project progresses and will submit a revised application to the AUC for the 423L project once it has been prepared.

Project details

The proposed Red Deer Area Transmission Development is divided into five stages.

  • Stage 1substation upgrades: upgrading six substations
  • Stage 2transmission line rebuilds: rebuilding nearly 75 kilometres of existing transmission lines in the Red Deer and Sylvan Lake areas
  • Stage 3new substations and transmission lines: building new substations near Ponoka, Innisfail and Didsbury and building approximately 50 kilometres of new transmission lines near the substations and east of Lacombe
  • Stage 4removing existing transmission lines: removing approximately 75 kilometres of transmission line from Wetaskiwin to Lacombe and approximately 25 kilometres of transmission line from Red Deer to Innisfail
  • Stage 5 - 166L transmission line rebuild: rebuilding approximately 15 kilometres of existing transmission line and upgrading an existing substation near Didsbury

Listen to our radio advertisements...

Newsletters and maps

August 2014

January 2014

July 2013

January 2013

November 2012

August 2012

November 2011

June/July 2011

August 2014

January 2014

August 2013

July 2013

May 2013

February 2013

June 2012

February 2012

January 2012

July 2011

   

In This Section
Projects
Rewarding Careers at AltaLink
Rewarding Careers at AltaLink
At AltaLink, we are doing everything in our power to attract the best and brightest.
Did You Know?
Workplace Safety at AltaLink
The average four-person family in Alberta today has 20 'instant-on' electronics such as laptops, DVD players, music device chargers and cell phone chargers.