• Central Alberta Transmission Projects

Red Deer Area Transmission Development

Project overview

Red Deer and the surrounding areas have grown significantly in recent years and the demand for electricity has increased. Transmission system reinforcements are required to make sure homes, farms and businesses continue to have a reliable supply of electricity for years to come.

Stage 1 of the development was completed in late 2013. On July 29, 2014, AltaLink received approval from the Alberta Utilities Commission (AUC) to construct componants that fall under stages 2 and 3 of the development.

Construction activities are currently underway in the Ponoka, Didsbury, Sylvan Lake and Red Deer areas. Construction in the Innisfail area is scheduled to begin in the summer or fall of 2015. Construction on all project components is expected to be complete by the summer or fall of 2016.

Click here for the typical stages of substation construction.
Click here for the typical stages of transmission line construction.

More information about each stage of the project, including newsletters and maps can be found below.

Project updates

Highway 2 lane closures and speed reductions near the City of Red Deer: July 2015

Lane closures and speed reductions will allow for the safe construction of the transmission line near Highway 2 and  32nd Street. We thank you for your patience throughout the construction process. Traffic controls and signage will be used to help direct the flow of highway traffic near 32nd Street during the following times:

July 20: Speed will be reduced to 80 km/h from 10 a.m. to 6 p.m. for both directions of traffic

July 21: Speed will be reduced to 80 km/h from 8 a.m. to 6 p.m. for both directions of traffic

July 22: Speed will be reduced to 80 km/h from 8 a.m. to 6 p.m. for both directions of traffic

July 23: Speed will be reduced to 80 km/h from 8 a.m. to 6 p.m. for both directions of traffic

July 24: Speed will be reduced to 80 km/h from 8 a.m. to noon for both directions of traffic

July 28: Single northbound lane closure and speed will be reduced to 80 km/h from 10 a.m. to noon

 

Lane closures in the City of Red Deer: July 2015

To allow for the safe construction of the transmission line near Taylor Drive and 54th Avenue we will require periodic lane closures. We thank you for your patience throughout the construction process. Traffic controls and signage will be used to help direct the flow of traffic during the following times:

July 28: Single lane closures for Taylor Drive in both directions near 54th Avenue from 8:00 a.m. until 6:00 p.m.

 

Path and lane closures in the City of Red Deer May - August, 2015 

In early May we plan to begin removing the existing portion of the 80L transmission line in the Riverlands and West Park areas. This work will take place along the riverbank southwest of Taylor Drive to the area just north of Welton Crescent and along Walker Boulevard towards Highway 2. During construction there will be periodic pathway and lane closures in the Riverlands and West Park areas.

  • Walker Boulevard traffic will be reduced to one lane while work is taking place in the area. Parking along Walker Boulevard will not be allowed during this time.

 

Read AltaLink's letter to the editor of the Red Deer Advocate - printed on Friday, October 10, 2014

There has been some misinformation in the public recently about AltaLink's Red Deer Area Transmission Development. On October 7, 2014 AltaLink submitted a letter to the editor in order to clarify details about the project and AltaLink's processes, especially with respect to the portion of the project that goes through the Pines neighbourhood in the City of Red Deer.

New transmission line east of Lacombe (423L) 
As part of Stage 3 of the development, AltaLink is also proposing to build a new transmission line, called 423L, east of Lacombe. AltaLink included this component in the original application that was filed with the AUC but we are continuing to look at our options for the proposed new transmission line. As a result, the AUC has postponed its consideration of the 423L component. AltaLink is continuing to communicate with stakeholders near the proposed 423L transmission line as the project progresses and we submitted a revised application to the AUC for the 423L project on October 6, 2014.

Project details

The proposed Red Deer Area Transmission Development is divided into five stages.

  • Stage 1substation upgrades: upgrading six substations
  • Stage 2transmission line rebuilds: rebuilding nearly 75 kilometres of existing transmission lines in the Red Deer and Sylvan Lake areas
  • Stage 3new substations and transmission lines: building new substations near Ponoka, Innisfail and Didsbury and building approximately 50 kilometres of new transmission lines near the substations and east of Lacombe
  • Stage 4removing existing transmission lines: removing approximately 75 kilometres of transmission line from Wetaskiwin to Lacombe and approximately 25 kilometres of transmission line from Red Deer to Innisfail
  • Stage 5 - 166L transmission line rebuild: rebuilding approximately 15 kilometres of existing transmission line and upgrading an existing substation near Didsbury

Listen to our radio advertisements...

Newsletters and maps

February 2015

 January 2015

October 2014

August 2014

January 2014

July 2013

January 2013

November 2012

August 2012

November 2011

June/July 2011

December 2014

October 2014

August 2014

January 2014

August 2013

July 2013

May 2013

February 2013

June 2012

February 2012

January 2012

July 2011

   

In This Section
Projects
Rewarding Careers at AltaLink
Rewarding Careers at AltaLink
At AltaLink, we are doing everything in our power to attract the best and brightest.
Did You Know?
Workplace Safety at AltaLink
A reliable transmission system keeps costs low by connecting diverse sources of power generation to the grid.