• Northern Alberta Transmission Projects

908L and 904L transmission line projects

New 908L transmission line

 

904L transmission line rebuild

 

Project overview

Construction is underway on the 908L and 904L transmission line projects.

The Alberta Electric System Operator (AESO) has requested AltaLink complete system upgrades in the Edmonton region to:

  • remove bottlenecks which restrict transmission line capacity
  • address the changes in Alberta’s electric grid due to the future retirement of a coal-fired electricity generator at Wabamun and the growth of wind generated electricity in southern Alberta
  • meet the increasing electrical demand in Edmonton and the northeast region 

Project details

New 908L transmission line: AltaLink is building 12 kilometres of new transmission line, named 908L, between the Keephills substation area and an existing transmission line, named 904L, near Jack Fish Lake.

904L transmission line rebuild: AltaLink is rebuilding 50 kilometres of an existing transmission line, named 904L, between the Jack Fish Lake area and the Petrolia substation located in the City of Edmonton.

Anticipated project schedule

Although we attempt to follow the anticipated project schedule it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Project Schedule
June 2010 Consultation and notification complete
July 2010 Filed application with the Alberta Utilities Commission (AUC)
September 2011  Project approved by the AUC
Fall 2011 Construction began 
Spring 2013 Complete construction

Newsletters and maps

Construction information

March 2012

October 2011

New 908L transmission line 

November 2009

March/April 2009

904L transmission line rebuild 

August/September 2009

June/July 2009

In This Section
Projects
Rewarding Careers at AltaLink
Rewarding Careers at AltaLink
At AltaLink, we are doing everything in our power to attract the best and brightest.
Did You Know?
Workplace Safety at AltaLink
Since the energization of AltaLink's southwest 240 kV transmission line, Albertans now have access to twice as much clean, green wind power.