Construction is underway on the 908L and 904L transmission line projects.
The Alberta Electric System Operator (AESO) has requested AltaLink complete system upgrades in the Edmonton region to:
New 908L transmission line: AltaLink is building 12 kilometres of new transmission line, named 908L, between the Keephills substation area and an existing transmission line, named 904L, near Jack Fish Lake.
904L transmission line rebuild: AltaLink is rebuilding 50 kilometres of an existing transmission line, named 904L, between the Jack Fish Lake area and the Petrolia substation located in the City of Edmonton.
| Project Schedule | |
|---|---|
| June 2010 | Consultation and notification complete |
| July 2010 | Filed application with the Alberta Utilities Commission (AUC) |
| September 2011 | Project approved by the AUC |
| Fall 2011 | Construction began |
| Spring 2013 | Complete construction |
Construction information
March 2012
October 2011
New 908L transmission line
November 2009
March/April 2009
904L transmission line rebuild
August/September 2009
June/July 2009