The routes in this map represent potential route options. If the project is approved, only one line will be built.
The Castle Rock Ridge Wind Farm Connection is part of an area transmission development called the Southern Alberta Transmission Reinforcement (SATR). This reinforcement includes new transmission lines and upgrades to the electric system in southern Alberta. These projects will connect new wind-generated power to Alberta’s electric system and strengthen the transmission system in the area.
The project includes:
| Project schedule | |
|---|---|
| November 2011 | Start project construction |
| March 2012 | Complete project construction |
November 2011
November 2009
June 2009