Leduc 325s Substation Transformer and Breakers Addition Project

AltaLink is proposing a series of upgrades at the Leduc Substation located in the city of Leduc. FortisAlberta has requested these upgrades to the electric system to help support the power demands of the industrial and commercial activities in the area and to ensure residences continue to have a reliable supply of power.

This project includes:

  • one new switchgear building
  • one new 138/25 kV transformer
  • one new 138 kV circuit breaker
  • six new 25 kV circuit breakers
  • other associated equipment


Project Status:
consultation

Anticipated Project Schedule

Winter /Spring 2016 Start Construction
Summer 2016 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing