Maxim Deerland Peaking Station

AltaLink is proposing to upgrade the existing Deerland 13S substation and build a transmission line to connect it to the customer-planned Skaro 109S substation.

This project includes:

  • adding a new breaker to the existing Deerland 13S substation
  • the removal of 100 metres (330 feet) of transmission line
  • constructing 150 metres (490 feet) of new transmission line

Project Status:
construction

Anticipated Project Schedule

October 2017 Start Construction
February 2017 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2017 AltaLink Site by Media Dog