Al Rothbauer 321S Substation Interconection

AltaLink is proposing to construct a new switching station in the City of Medicine Hat, along with perform several transmission line modifications. Modifications to the Medicine Hat 138 kV Transmission Project are required to construct this project. This project involves:

  • constructing a new switching station, to be called the Al Rothbauer Substation
  • reconfiguring transmission line connections into the existing Medicine Hat Substation
  • connecting existing transmission lines into the proposed Al Rothbauer Substation
  • salvaging 120 metres (395 feet) of transmission line
  • salvaging equipment from the existing Medicine Hat Substation

Project Status:
approved

Anticipated Project Schedule

Summer/Fall 2016 Start Construction
Spring 2017 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.