Plamondon Substation Upgrade

AltaLink is proposing upgrades to the existing Plamondon Substation located in Lac La Biche County in the Hamlet of Plamondon. 

The project includes:

 

  • installing one new 138/25 kV transformer 
  • installing one new 138 kV circuit breaker
  • relocating associated 25 kV equipment 

Project Status:
construction

Anticipated Project Schedule

Spring 2016 Start Construction
Winter 2016 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.