ATCO Power Heartland Generating Station Interconnection

AltaLink is proposing to upgrade its transmission system in the Fort Saskatchewan area to connect ATCO Power's proposed Heartland Generating Station to the electric system.

This project includes:

  • constructing approximately two kilometres of new transmission line
  • adding new equipment to the Josephburg Substation

Project Status:
application

Anticipated Project Schedule

February 2018 Start Construction
August 2020 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2017 AltaLink Site by Media Dog