Bullshead Substation Upgrade

The proposed project involves adding new equipment to the Bullshead 523S Substation, located southwest of the City of Medicine Hat in Cypress County, and modifying two transmission lines. Also, to accommodate the upgrades to the Bullshead Substation, a fenceline expansion will be required. The upgrades to the Bullshead Substation include:

  • adding one new 138 kV transformer
  • adding one new 138 kV circuit breaker
  • salvaging one 25 kV circuit breaker
  • adding one new 25 kV circuit breaker
  • re-terminating the 676L transmission line and a Fortis distribution line
  • adding or modifying associated substation equipment 

Project Status:
approved

Anticipated Project Schedule

Fall 2016 Start Construction
Spring 2017 Complete Construction