Fortis Lac La Biche Substation Transformer Addition

The proposed project involves upgrades to the Lac La Biche Substation. All work will occur within the existing fenceline on AltaLink's leased land and no fence expansion will be required. The upgrades to the Lac La Biche Substation include:

  • installing one new 138/25 kV transformer
  • installing one new 138 kV breaker
  • installing one new 25 kV breaker
  • relocation of existing 25 kV feeder breaker
  • installing other associated equipment 

Project Status:
construction

Anticipated Project Schedule

April 2017 Start Construction
Fall 2017 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.