Benbow Telecommunications Tower Replacement

AltaLink is proposing to replace the telecommunications tower at the Benbow Substation. The existing telecommunications tower is nearing the end of its lifecycle and needs to be replaced for maintenance reasons.

A new tower is required to maintain a communications link with the electric system and because no existing infrastructure is suitable for the antenna. Replacing the tower will allow us to maintain the safety and reliability of the electric system in the area.


Project Status:
consultation

Anticipated Project Schedule

April 2017 Start Construction
June 2017 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.