AltaLink is proposing to upgrade the wires on the two portions of the existing 807L line and replace some existing structures to help meet the growing industrial demand for power in the Fort Saskatchewan area.


Project Status:
approved

Anticipated Project Schedule

May 2017 Start Construction
July 2017 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.