Suncor Granlea Connection Project

Suncor has requested a connection to the transmission system for their proposed Forty Mile Wind Power Project. The 400 megawatt (MW) Forty Mile Wind Power Project will supply electricity to the grid via two proposed substations: the Granlea Substation and the Maleb Substation. 


Project Status:
consultation

Anticipated Project Schedule

July 2019 Start Construction
September 2019 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2017 AltaLink Site by Media Dog