Blackfalds Substation Upgrade Project

AltaLink is proposing to upgrade equipment at the Blackfalds 198S Substation, located north of the town of Blackfalds to maintain the safety and reliability of the electric system.

This project includes:

  • replacing two 138/25 kV transformers with two new higher capacity 138/25 kV transformers
  • salvaging one 25 kV voltage regulator
  • adding two 25 kV circuit breakers
  • adding one 138 kV circuit breaker

Project Status:
construction

Anticipated Project Schedule

Winter 2016 Start Construction
Summer 2016 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.