Central East Transfer-Out Project

The proposed Central East Transfer-Out Project is located in the counties of Red Deer, Lacombe and Stettler includes:

  • Approximately 55-60 kilometres of new 240 kilovolt (kV) transmission line connecting the Gaetz Substation, located east of the City of Red Deer, to a new ATCO Electric line, located southeast of the Village of Alix

  • Installing new equipment at the Gaetz Substation


 

 

Project Status:
application

Anticipated Project Schedule

Fall 2021 Start Construction
2023 (first circuit); 2027-2029 (second circuit - if needed) Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2021 AltaLink Site by Media Dog