Calder 9037R Radio Site Telecommunications Tower Replacement

AltaLink is proposing toremove the existing telecommunication tower at the existing North Calder 37S substation, located in northwest Edmonton, and construct a new tower at the proposed 9037R Calder radio site.

This project includes:

  • removing the existing tower at the substation
  • constructing a new, taller tower and control building at the proposed 9037R Calder radio site

Project Status:
complete

Anticipated Project Schedule

May 2017 Start Construction
September 2017 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing