Hayter 277S Substation Upgrade

AltaLink is proposing to upgrade its existing Hayter 277S Substation approximately 20 kilometres (12 miles) northeast of Provost. Upgrades are required to help ensure a reliable supply of power and to meet the increased residential, commercial and industrial demand for electricity in the area.

This project includes:

  • a new transformer
  • a new circuit breaker

Project Status:
complete

Anticipated Project Schedule

April 2017 Start Construction
September 2017 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.