This project is part of the Province of Alberta's Southwest Calgary Ring Road Project.
This project includes:
- removing approximately 2.5 kilometres (1.5 miles) of 240 kilovolt (kV)/138 kV double circuit steel lattice transmission line from Tsuu T'ina Nation land and relocating it underground within the Transportation/Utility Corridor (TUC) south of Glenmore Trail and west of 37 Street Southwest
- rebuilding approximately one kilometre (0.6 miles) of two pole 138 kV transmission line from Tsuu T'ina Nation land and relocating as a double circuit 138 kV transmission line on the south side of Highway 8 within the TUC
- relocating approximately 0.5 kilometres (0.3 miles) of a 240 kV double circuit transmission line further west along Sarcee Trail
- reconfiguring existing transmission lines at the Sarcee Substation to accommodate the proposed interchange at Sarcee Trail and Highway 8
Detailed Project Schedule | |||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Early 2015 | Notify and consult with stakeholders | ||||||||||||||||||||||||||||||||||||||||||||||||
Fall 2015 | File application with Alberta Utilities Commission (AUC) | ||||||||||||||||||||||||||||||||||||||||||||||||
November 2016 | Start construction if project approved | ||||||||||||||||||||||||||||||||||||||||||||||||
Summer 2018 | Complete construction |
- October 2017
- Construction update
- Construction update
- August 2017
- Construction update
- Construction update
- July 2017
- Construction update
- May 2017
- Construction open house panels
- Lakeview construction traffic accommodation plans
- January 2017
- Construction newsletter
- Construction map
- October 2016
- Notice of approval
- Notice of approval map
- November 2015
- Notice of Filing Letter
- September 2015
- Project update newsletter
- Project update map
- February 2015
- Project newsletter
- Project map
- Alberta Transportation letter
Project Status:
complete
Anticipated Project Schedule
November 2016 | Start Construction |
Summer 2018 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.