The Cooking Lake 138 kV Transmission Line and Substation Upgrade project is part of the South and West of Edmonton Area Transmission Development. This area has grown significantly in recent years and the demand for electricity has increased. Transmission system reinforcements are required to make sure residents, businesses and industry continue to have a reliable supply of electricity for years to come.
The proposed project includes:
- building approximately 25 km (15 miles) of double circuit 138 kV transmission line from the existing 780L line to the Cooking Lake 522S Substation
- potentially modifying a portion of the 780L line and the 174L line to connect to the new double circuit line
- modifications to and expansion of the fence line at the Cooking Lake 522S Substation
Detailed Project Schedule | |||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Summer 2013 - Summer 2014 | Notify and consult with stakeholders | ||||||||||||||||||||||||||||||||||||||||||||||||
Fall 2015 | File application with Alberta Utilities Commission (AUC) | ||||||||||||||||||||||||||||||||||||||||||||||||
November 2016 | Start construction | ||||||||||||||||||||||||||||||||||||||||||||||||
December 2017 | Complete construction |
- November 2016
- Construction newsletter
- Construction map
- August 2016
- Notice of approval
- Notice of approval map
- November 2015
- Notice of Filing Letter
- May 2015
- Stakeholder Update Letter - Preferred route changes
- Stakeholder Update Letter - Alternate route changes
- Updated Focus Photo Map 1
- Updated Focus Photo Map 2
- Updated Focus Photo Map 3
- Updated Focus Photo Map 4
- Updated Focus Photo Map 5
- September 2014
- Stakeholder update - postcard
- May 2014
- Volume 3 newsletter
- Detail Photo Map
- Strip Mosaic Map
- Strip Index Map
- AESO Need Overview
- March 2014
- Open House Booklet
- January 2014
- Volume 2 newsletter
- Detail Photo Map
- Strip Mosaic Map
- Strip Index Map
- AESO Need Overview
- July 2013
- Volume 1 newsletter
- Detail Photo Map
- Strip Mosaic Map
- Strip Index Map
- AESO Need Overview
Project Status:
complete
Anticipated Project Schedule
November 2016 | Start Construction |
December 2017 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.