AltaLink and ATCO Electric are working to connect the Jasper area to the Alberta electric system to ensure residents continue to have a reliable supply of electricity.


AltaLink and ATCO Electric are working to connect the Jasper area to the
Alberta electric system to ensure residents continue to have a reliable
supply of electricity. AltaLink’s scope in the proposed project includes:

  • constructing approximately eight to nine kilometres (five miles) of new 69 kV (kilovolt) transmission line
  • expanding the existing Watson Creek Substation
  • adding new equipment to the Watson Creek Substation
  • modifying one existing structure at the Watson Creek Substation
  • adding three new structures, one of which will support a line bypass switch, outside of the Cold Creek Substation

Project Status:
complete

Anticipated Project Schedule

Fall 2017 Start Construction
Spring 2018 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.