AltaLink and ATCO Electric are working to connect the Jasper area to the Alberta electric system to ensure residents continue to have a reliable supply of electricity.
AltaLink and ATCO Electric are working to connect the Jasper area to the
Alberta electric system to ensure residents continue to have a reliable
supply of electricity. AltaLink’s scope in the proposed project includes:
- constructing approximately eight to nine kilometres (five miles) of new 69 kV (kilovolt) transmission line
- expanding the existing Watson Creek Substation
- adding new equipment to the Watson Creek Substation
- modifying one existing structure at the Watson Creek Substation
- adding three new structures, one of which will support a line bypass switch, outside of the Cold Creek Substation
- February 2017
- Project update
- December 2016
- Notice of application filing
- Map
- August 2016
- Project Update
- DP Map
- FP Map
- Updated AESO Need Overview
- May 2016
- Newsletter
- DP Map
- Strip maps
- DP Map - Cold Creek Substation
- FP Map
- AESO Need Overview