Suncor has requested a connection to the transmission system to connect AltaLink’s existing Whitla Substation at NW 33-7-9 W4 to Suncor’s Maleb Substation.
We are proposing to build approximately 2.5 to 3 kilometres of 240 kilovolt (kV) transmission line. The final transmission line length is dependent on the final route selected, and approved, by the Alberta Utilities Commission (AUC).
- November 2022
- AESO - Cancellation letter
- AltaLink - Cancellation letter
- December 2019
- Notice of project approval
- January 2019
- Notice of Application Filing
- November 2018
- AESO need overview update
- Project update
- August 2017
- Project newsletter
- Project map
- AESO need overview
- April 2017
- Project newsletter
- Project map
- AESO need overview