Coalspur Mines (operations) Ltd. (Coalspur) has requested a connection to the transmission system for their approved Vista Coal Mine Project. To facilitate this connection, Coalspur has approval to construct a new substation to be called Vista Substation. AltaLink is proposing to construct a transmission line, operated and maintained by AltaLink, to connect the Vista Substation to the electric system.


Project Status:
approved

Anticipated Project Schedule

Fall 2018 Start Construction
Winter 2018 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.