Central East Transfer-Out Project

The approved Central East Transfer-Out Project is located in the counties of Red Deer, Lacombe and Stettler.

The Alberta Utilities Commission approved:

  • AltaLink’s south alternate route for a new double circuit 240 kilovolt transmission line between AltaLink’s existing Gaetz Substation, located east of the City of Red Deer, to ATCO Electric’s approved transmission line

  • New equipment to be installed at the Gaetz Substation


Project Status:
approved

Anticipated Project Schedule

Late 2024 Start Construction
TBD Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2023 AltaLink