This proposed project involves equipment upgrades at the existing 545S Provost Substation, located at NW-7-39-2-W4, west of the town of Provost in the Municipal District of Provost.
The proposed substation upgrade includes installing one new switchgear building, installing five new 25 kilovolt (kV) circuit breakers, and removing aging equipment.
Please note that this Provost Substation upgrade project is separate from the Fortis Provost Reliability Upgrade project that you may have received information about earlier last year.