14S Devon Radio Telecommunications Tower Replacement

This project involves replacing the existing telecommunications tower at the Devon Substation with a new, taller tower. The existing telecommunications tower is a wood pole, approximately 16.5 metres tall. The tower was constructed in 1975 and has been chosen for replacement due to its age.


Project Status:
complete

Anticipated Project Schedule

June 2019 Start Construction
August 2019 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.