The proposed project involves equipment upgrades at the existing Duchess 339S Substation, approximately 1.5 km west of the Village of Duchess in the County of Newell, NW-31-20-14-W4.
The project involves removing a faulting switch and replacing it with a 138kV circuit breaker.
- April 2020
- Notice of approval
- March 2019
- Project newsletter
- Project map
Project Status:
construction
Anticipated Project Schedule
April 2020 | Start Construction |
November 2020 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.