186S Dry Creek Telecommunications Tower Extension Project

This project involves building an extension onto the existing telecommunications tower at the 186S Dry Creek Substation. The existing tower is a self-supporting steel lattice structure approximately 27 metres (m) tall. The extension is approximately 7.5 m. After the extension, the tower will be approximately 35 m tall, including a lightning rod.


Project Status:
complete

Anticipated Project Schedule

September 2019 Start Construction
December 2019 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2023 AltaLink