We rebuilt portions of the 113L transmission line to ensure that a safe and reliable supply of power is available for years to come. The project involved rebuilding approximately 23 kilometres of the overhead portion of 113L line that runs from the Town of Canmore to the Kananaskis River
Vegetation management activities will occur along the line throughout 2023. Depending on where you are in relation to the project, you may see or hear ongoing tree and vegetation management, including logging equipment and trucks. Cut trees will be taken away from the project area.
- January 2023
- Construction update for January 2023
- August 2022
- Construction update for August to November 2022
- December 2021
- Construction update for January to April 2022
- October 2021
- Notice of project approval
- May 2021
- Notice of filing and project update
- COVID-19 update
- November 2020
- Project update letter
- August 2020
- Project update newsletter
- COVID-19 update
- Detail base map
- Detail photo map
- Strip maps
- February 2020
- Project newsletter
- Detail base map
- Detail photo map
- Strip maps
Project Status:
vegetation-management
Anticipated Project Schedule
January 2022 | Start Construction |
January 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.