The proposed project involves constructing a new telecommunications tower at the Westlock Algonquin Power I318S Substation in SW-1-63-2-W5. This will include removing the existing 24.4 metre wood pole telecommunications tower inside the substation, and installing one new self-supporting tower.
- December 2020
- Notice of filing and approval
- August 2020
- Project newsletter
- Detail photo map
Project Status:
consultation
Anticipated Project Schedule
Spring 2021 | Start Construction |
Summer 2021 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.