Turning Point Generation (TPG) has requested a connection to the transmission system for their proposed pumped hydro energy storage (PHES) project. To facilitate this connection, AltaLink is proposing to construct a transmission line, operated and maintained by AltaLink, to connect TPG’s proposed new substation to the electric system. Although AltaLink’s project is separate from TPG’s project, it is required to facilitate the connection of their project.
- January 2021
- Project update letter
- Detail photo map
- September 2020
- Project newsletter
- COVID-19 project letter
- Detail photo map
- AESO need overview
Project Status:
consultation
Anticipated Project Schedule
January 2022 | Start Construction |
June 2022 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.