Enerfin Bullshead Substation Upgrade

Enerfin Energy Company of Canada Inc. (Enerfin) has requested a connection to the transmission system for its proposed Winnifred Wind Project. To facilitate this connection, Enerfin is proposing to construct a new collector substation and transmission line which will connect to AltaLink’s existing Bullshead Substation. AltaLink is seeking to upgrade the Bullshead Substation to accommodate the connection.


Project Status:
application

Anticipated Project Schedule

April 2022 Start Construction
January 2023 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2023 AltaLink