Enerfin Energy Company of Canada Inc. (Enerfin) has requested a connection to the transmission system for its proposed Winnifred Wind Project. To facilitate this connection, Enerfin is proposing to construct a new collector substation and transmission line which will connect to AltaLink’s existing Bullshead Substation. AltaLink is seeking to upgrade the Bullshead Substation to accommodate the connection.
- August 2021
- Notice of application filing
- January 2021
- Project Newsletter
- Detailed Photo Map
- AESO Need Overview
Project Status:
application
Anticipated Project Schedule
April 2022 | Start Construction |
January 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.