BowArk Queenstown Power Plant Interconnection

AltaLink is proposing to construct a new transmission line to connect the proposed BowArk Queenstown power plant to the electric grid.

This project includes:

  • a new 138 kV tranmission line
  • extending an existing transmission line
  • modifications to the existing Queenstown Substation

Project Status:
cancelled

Anticipated Project Schedule

June 2016 Start Construction
November 2016 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2023 AltaLink