A transformer at AltaLink’s Cope Creek Substation is currently not in use. AltaLink is proposing to salvage the 138/13.8 kV transformer, and install it at another substation. The Cope Creek Substation is located at SW-24-25-5-W5 in Rocky View County.
Project Status:
consultation
Anticipated Project Schedule
Spring 2021 | Start Construction |
Summer 2021 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.