Coalspur Substation Upgrade

We are proposing to upgrade equipment at the existing Coalspur 426S Substation to ensure a reliable supply of electricity is available in the area for years to come.

To replace aging equipment at the Coalspur Subtation, AltaLink is proposing to install one new 138 kV circuit breaker. No fence expansion will be required for this project.


Project Status:
complete

Anticipated Project Schedule

June 2021 Start Construction
September 2021 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates

Back to Project Map Back to Project Listing

©2023 AltaLink