Dunmore Solar Inc. (Dunmore Solar) is proposing to build a new substation as part of their Dunmore Solar Power project. To connect their proposed substation to the grid, AltaLink is proposing to construct a new transmission line between the proposed substation and an existing transmission line in the area.
Although AltaLink’s project is required to facilitate the connection of Dunmore Solar’s project, it is a separate project. Dunmore Solar has consulted separately on their proposed substation and facility.
Project Status:
construction
Anticipated Project Schedule
January 2023 | Start Construction |
March 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.