Buffalo Plains Wind Farm Inc. (Buffalo Plains) is proposing to build a new transmission line as part of their Buffalo Plains wind farm project. To connect their proposed facility to the grid, AltaLink is proposing equipment upgrades at its Milo Substation, as well as modifications to an existing transmission line just outside the substation.
Although AltaLink’s project is required to facilitate the connection of the Buffalo Plains project, it is a separate project. Buffalo Plains will consult separately on their proposed transmission line, substation and facility.
Project Status:
application
Anticipated Project Schedule
October 2022 | Start Construction |
December 2022 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.