To accommodate its North of Yellow Head Road Upgrades, Strathcona County has requested the relocation of a portion of AltaLink’s 138 kilovolt (kV) 700L transmission line.
This proposed project involves relocating approximately two kilometres of the 700L transmission line that is located north of Highway 16 in Strathcona County along Range Road 231. We are proposing to relocate the line up to approximately 70 metres to the east to accommodate Strathcona County’s plans to widen the road.
Project Status:
construction
Anticipated Project Schedule
January 2023 | Start Construction |
March 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.