To connect RES’s approved Hilda Wind Power Project to the grid, AltaLink is proposing upgrades to its transmission system in the area.
This project is located in Cypress County. Part of the proposed project is located approximately 10 kilometres northwest of the hamlet of Hilda in NW-29-18-1-W4M, and part of it is located approximately 15 kilometres northeast of the city of Medicine Hat at the existing Chappice Lake Substation in SW-22-14-4-W4M.
Project Status:
application
Anticipated Project Schedule
July 2022 | Start Construction |
August 2022 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

