To connect Renewable Energy Systems Canada Inc.’s (RES) approved Forty Mile Wind Power Plant to the grid, AltaLink is proposing upgrades to its transmission system in the area, including the construction of a new switching station, modifications to an existing structure, addition of one structure, and installation of approximately one kilometre of fibre optic cable.
Although AltaLink’s project is required to facilitate the connection of the Forty Mile Wind Power Plant, it is a separate project. In addition to the approved Forty Mile Wind Power Plant, there is a proposed RES 240 kilovolt (kV) transmission line project associated with it. RES will be consulting separately on their projects.
- November 2022
- Notice of project approval
- July 2022
- Notice of application filing
- January 2022
- Project newsletter
- Detail photo map
- COVID-19 update letter
- AESO need overview
Project Status:
construction
Anticipated Project Schedule
March 2023 | Start Construction |
November 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.