To connect BluEarth Renewables Inc’s (BluEarth) approved Wheatcrest Solar Project to the grid, AltaLink is proposing upgrades to its transmission system in the area. AltaLink’s project is located in the Municipal District of Taber, approximately 12 kilometres north of the Village of Enchant.
To connect the Wheatcrest Solar Project to the grid, AltaLink is proposing updates along an existing 138 kilovolt (kV) transmission line (called 763AL) and in the existing Enchant Substation.
- February 2023
- Project update letter
- Detail photo map
- December 2022
- Notice of project approval
- August 2022
- Notice of application filing
- February 2022
- Project newsletter
- Detail photo map 1
- Detail photo map 2
- Electric and Magnetic Fields and Radio Frequency Information
- COVID-19 project letter
- AESO need overview
Project Status:
construction
Anticipated Project Schedule
January 2023 | Start Construction |
Winter 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.