The transformer at the East Airdrie Substation is reaching the end of its life cycle, and we are proposing to replace it. This project is part of AltaLink’s Capital Replacement and Upgrade program and will ensure that the area continues to have a reliable source of electricity for years to come.
- August 2022
- Notice of application filing and project approval
- May 2022
- Project newsletter
- Detail photo map
Project Status:
approved
Anticipated Project Schedule
July 2022 | Start Construction |
September 2022 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.