East Airdrie Substation Transformer Replacement

The transformer at the East Airdrie Substation is reaching the end of its life cycle, and we are proposing to replace it. This project is part of AltaLink’s Capital Replacement and Upgrade program and will ensure that the area continues to have a reliable source of electricity for years to come.


Project Status:
approved

Anticipated Project Schedule

July 2022 Start Construction
September 2022 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

Subscribe to Updates