We are proposing to upgrade equipment at the existing Suffield 895S Substation to ensure a reliable supply of electricity is available in the area for years to come. AltaLink’s Suffield Substation is located at NW-3-15-9 W4, approximately one kilometre north of the Hamlet of Suffield in Cypress County.
The proposed project includes:
• replacing a 25 kilovolt (kV) bus with a switchgear building and salvaging the bus
• expanding the existing control building
- August 2022
- Notice of project approval
- July 2022
- Project newsletter
- Detail photo map
Project Status:
complete
Anticipated Project Schedule
September 2022 | Start Construction |
March 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.