Suffield Substation Upgrade

We are proposing to upgrade equipment at the existing Suffield 895S Substation to ensure a reliable supply of electricity is available in the area for years to come. AltaLink’s Suffield Substation is located at NW-3-15-9 W4, approximately one kilometre north of the Hamlet of Suffield in Cypress County.

The proposed project includes:
• replacing a 25 kilovolt (kV) bus with a switchgear building and salvaging the bus
• expanding the existing control building


Project Status:
complete

Anticipated Project Schedule

September 2022 Start Construction
March 2023 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.