Sol Aurora Solar Battery Connection

To connect Sol Aurora Ltd.’s (Sol Aurora) proposed Sol Aurora Solar Battery project to the grid, AltaLink is proposing equipment upgrades to its transmission system in the area.


Project Status:
consultation

Anticipated Project Schedule

January 2024 Start Construction
April 2024 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.