AltaLink is proposing to relocate a portion of the existing 240 kilovolt (kV) transmission line (called 922L/926L) that is located in Parkland County in SW-17-52-4-W5. This portion of line is being affected by water and ice in the winter. There is currently no risk to public safety and electricity service, but relocating this portion will allow us to maintain the safety and reliability of the transmission line in the future.
- January 2023
- Notice of application filing and project approval
- August 2022
- Project newsletter
- Detail photo map
Project Status:
consultation
Anticipated Project Schedule
October 2022 | Start Construction |
January 2024 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.