This was previously called the East Palliser Transmission Project. The East Palliser Transmission Project began in 2010 and included connecting the Wild Rose 1 and Wild Rose 2 wind farms to the electric system. The project was approved in 2012 but was put on hold. The Wild Rose 1 portion of the project has been cancelled.
Wild Rose 2 Wind LP (Wild Rose) is now proceeding with the Wild Rose 2 Wind Farm project, but with minor changes that include a new substation location. AltaLink will file an amendment to its original application that reflects the changes to the project.
Project Status:
consultation
Anticipated Project Schedule
August 2022 | Start Construction |
June 2023 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.

