To connect the Kirkcaldy Solar Energy Partnership (Kirkcaldy) Solar Project to the grid, AltaLink is proposing modifications to its transmission system in the area.
Kirkcaldy is constructing a new 240 kilovolt (kV) transmission line located approximately 10 kilometres east of the Town of Nanton.
Kirkcaldy is considering two connection points along AltaLink's existing 1037L/1038L transmission line. To accommodate the connection, AltaLink is proposing to modify its transmission line at one of two potential locations, depending on the final connection point determined by Kirkcaldy.
Project Status:
consultation
Anticipated Project Schedule
March 2024 | Start Construction |
September 2024 | Complete Construction |
Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.