Spring Coulee Substation Upgrade

We are proposing to upgrade equipment at the existing Spring Coulee Substation to ensure a reliable supply of electricity is available in the area for years to come.

The proposed project involves equipment upgrades at the existing Spring Coulee Substation, located in Cardston County, approximately eight kilometres southwest of the Hamlet of Spring Coulee in SE-15-4-24 W4.


Project Status:
construction

Anticipated Project Schedule

July 2023 Start Construction
December 2023 Complete Construction

Although we attempt to follow the anticipated project schedule, it is subject to change. We will continue to provide you with updated schedule information as the project progresses.