**If you are looking for the Fidler to Chapel Rock Transmission Project, please click here.**
AltaLink began public consultation for this project in November 2009. We suspended work in December 2011 and waited for further direction from the Alberta Electric System Operator (AESO). We received direction from the AESO to resume work on the project and have filed our facilities application with the Alberta Utilities Commission (AUC). The AUC approved this project for construction on May 10, 2013.
The proposed project includes:
- building a new substation northeast of the Town of Pincher Creek
- building approximately five to nine kilometres of new 240 kV transmission line
- reconfiguring and removing some sections of existing transmission lines in the area
Detailed Project Schedule | |||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Summer 2012 | Notify and consult with stakeholders about preliminary routes | ||||||||||||||||||||||||||||||||||||||||||||||||
Fall 2012 | File application with the AUC | ||||||||||||||||||||||||||||||||||||||||||||||||
Fall 2013 | Start construction |
- July 2013
- Notice of project amendment letter
- Notice of project amendment map
- AESO Needs Identification Document amendment
- May 2013
- Notice of project approval
- November 2012
- Notice of application filing
- July 2012
- July 2012 newsletter
- Detail photo map
- Open house panels
- December 2011
- Alberta Utilities Commission decision letter
- May 2010
- Letter to stakeholders
- AESO Need Overview
- April 2010
- Letter to stakeholders
- Detail photo map
- Strip mosaic index map
- strip mosaic maps
- Image of typical 240 kV structure
- Image of typical 138 kV structure
- November 2009
- Volume 1 newsletter
- Detail base map
- detail photo map
- AESO need overview
- Good neighbours
- A dialogue on electric and magnetic fields